Energy & cooling · Page 2

Mining news and original analysis with dated primary sources.

10.09.2026
Cuentas signs a staged 24 MW West Texas mining power agreement

Cuentas signs a staged 24 MW West Texas mining power agreement

A September 23 SEC filing describes up to ten 2.4 MW container sets and about 4,200 ASIC miners, with $0.05/kWh energy pricing, revenue share and an 80% take-or-pay floor.

PNNL releases RATLLE method for large-load oscillation risk

PNNL releases RATLLE method for large-load oscillation risk

PNNL-39459 presents a three-stage workflow for screening, simulation and severity analysis. Case studies show modeled 50 MW cyclic loads can excite wide-area grid modes at resonance.

PNNL models data-center controls as grid-service resources

PNNL models data-center controls as grid-service resources

PNNL report PNNL-39553 models coordinated compute, cooling, battery and onsite generation controls on a modified IEEE 24-bus system. The results are simulations, not operating guarantees.

DOE selects 21 geothermal projects as mining power demand grows

DOE selects 21 geothermal projects as mining power demand grows

Five selected projects will test enhanced geothermal systems and 16 will drill for resource data. Up to $99 million is contemplated for initial work, but selections are not funding awards or new power for miners.

NERC computational-load standards pass initial ballot

NERC computational-load standards pass initial ballot

NERC says foundational reliability standards for data centers, AI clusters and cryptocurrency facilities passed an initial ballot. Results still require validation and the standards process continues.

DOE emergency order expands Carolinas grid options during late heat

DOE emergency order expands Carolinas grid options during late heat

The September 18–21 order lets Duke Energy Carolinas dispatch specified and backup resources when reliability is threatened. We explain what it means—and does not mean—for flexible mining loads.

DOE orders Schahfer units available to MISO through December 18

DOE orders Schahfer units available to MISO through December 18

The emergency order starts September 20 and concerns grid reliability, not a special rule for miners. Flexible-load operators should review curtailment and tariff assumptions.

Soluna’s Dorothy gets conditional ERCOT status for 100 MW

Soluna’s Dorothy gets conditional ERCOT status for 100 MW

Soluna reports conditional Base Load classification for Dorothy and a separate 50 MW request under study. What these milestones mean for a wind-linked mining campus.

Ethiopian miners receive 23% of contracted power: what the latest report confirms

Ethiopian miners receive 23% of contracted power: what the latest report confirms

Bloomberg’s September 15 report describes power allocation at 23% of mining contracts. Epic Mining’s earlier notices show that the restrictions did not begin on that date.

Canaan mined 44 BTC in August and advances Canadian heat reuse

Canaan mined 44 BTC in August and advances Canadian heat reuse

Canaan’s September 14 update reports 44 BTC mined in August, $0.043/kWh power costs and equipment installation at a Canadian greenhouse heat-recovery project.

Sangha’s 110.4 MW Texas campus gets conditional ERCOT status

Sangha’s 110.4 MW Texas campus gets conditional ERCOT status

ERCOT placed the planned campus in Batch Zero as Base Load, subject to audit and verification. About 19.9 MW is currently available; the rest is expected in 2028.

Cipher starts gas pipeline development for up to 2.5 GW

Cipher starts gas pipeline development for up to 2.5 GW

Lateral pipelines are intended to supply future generation across several data center sites. The capacity is planned, not already operating.